Obtained on 2073-02-20, renewed in 2075-02-20.
Signed with NEA for 7.25 MW on 29th Bhadra 2074.
2081/01/06
Obtained on 2076-05-26.
Syndicated loan agreement signed on 2077-07-04 with Kumari Bank Ltd. and Shangrila Development Bank.
Prepared in Ashad 2073.
Prepared in Ashwin 2076.
Approved on 2076-03-20.
Private Land: 24 Ropani purchased, 8.98 Ropani Compensated to Government
357 trees cut as per government approval along with compensation plantation work completed at 1:25 ratio
Implementing environmental plans as per the approved EIA.
Constructed 4 km road from Bhujung Village to Powerhouse.
4.1 km road constructed
Permanent camp blocks constructed
listed in SEBON ,pipeline priority no 4
20,00,000 nos